craftsmanship and a lot of material

Much, very much, material has to be supplied. Already 10 trucks in the first 2 weeks. The steel and cement comes from Kathmandu because of the heavy loads, more than 2 days driving, the sand and grit comes from a river bed about 6 hours drive from Sailung. cement more than 200 bags of grit supply quality steel JAG […]

1 bulldozer and 20 men

Bulldozer leveling the field Thanks to the new access road to the school site, trucks can reach the construction site. That will save a lot of lugging work. The bulldozer could also be used for 2 more days to collect stones for the protection wall and dig the large foundation holes. To add all this […]